Data Center FAQs
frequently asked questions
How do I develop a decommissioning plan?
Planning a Successful Project
A successful project requires planning and cooperation between data center personnel and the decommissioning vendor. The pdf shown below serves as a checklist for things to consider to ensure your team is ready and selects a vendor that meets the needs of your data center.
Data Center Decommissioning Plan
- Pre-planning to be done by data center personnel
- Initial information to provide to vendor
- Define in-scope and out-of-scope activities
- Determine your reporting requirements.
- Miscellaneous details to consider
1. Pre-Planning to be Done by Data Center
Inventory Preparation
- Compile a detailed inventory of all equipment to be decommissioned (rack location, make, model, serial number). Match to CMDB inventory.
- Develop diagram showing what equipment is targeted for decommissioning (if project is not total shutdown or cleanout)
- Identify additional assets for removal (cabling, e-waste, miscellaneous IT assets)
Stakeholder Identification
- Designate an on-site decision maker for the project.
- Assign project manager to oversee project (if different from on-site contact)
Contract and License Management
- Develop plan for leased equipment.
- Document software licenses, warranties, support contracts. Develop a software license migration/cancellation plan.
- Cancel or adjust hardware maintenance contracts.
Timeline Management
- Establish critical project timelines and deadlines.
- Determine cadence for scheduled check ins during project.
2. Initial Information to Provide to Vendor
- Data center address and operating hours
- Project scope and type (data center shutdown, hardware refresh in live environment, cage cleanout)
- List and location of hardware to be decommissioned
- Preferred project start and end dates
- Handling protocol for data bearing assets (data destruction requirements, such as NIST 800-88)
- Inventory tracking and reconciliation requirements
- Building security requirements
3. Site Survey and Project Planning
Scheduling a site visit with shortlisted vendors can help with project planning and ensuring on-time performance. This can be done in-person or as a remote event, if a visit is not possible.
- Map equipment to be decommissioned
- Define dedicated work areas for decommissioning team, with power and internet
- Confirm access points (loading dock, freight elevator)
- Identify staging areas for equipment as it is decommissioned
- Indicate presence of other contractors on-site and conflict management plans.
- Floor protection requirements
- Define security clearance requirements for field technicians
- Review space and access constraints (e.g., limited loading dock, restricted truck size, parking availability)
- Indicate how exceptions will be managed and resolved (project holds)
4. Confirm Scope of Decommissioning Activity
(In-Scope and Out-of-Scope Activities)
- Removal and disposal of power/network cables
- Will racks be removed or left in place?
- Will populated racks be shipped or decommissioned on-site?
- Tagging system for equipment to be decommissioned
- Electronic inventory data capture requirements
- Inventory count confirmation and discrepancy management
- Is on-site data destruction required?
- Recovery of parts for use as critical spares?
- Tracking and reporting requirements for data-bearing equipment
- Packing services and materials needed
5. Reporting Requirements
- Chain-of-custody reporting for data-bearing devices
- Certificate of Data Destruction information requirements
- Shipment documentation needs
- Inventory reporting for decommissioned equipment
- Stakeholder Reporting (accounting, risk management, data privacy and IT teams)
- Items processed per shipment/month/location
- Make, model, serial number tracking
- Inventory count matching (quality control)
- Equipment disposition (redeployed, sold, recycled)
- Sales price and net revenue tracking
- Parent/child tracking (rack, server, hard drive)
Miscellaneous Details
Special considerations depending on type of decommissioning project:
Enterprise – Shutdown
(Data center shutdown)
Completed project includes:
- Floor bolts will be removed to floor level
- All cabling will be removed
- Removal of all ancillary items
- Broom swept clean space
Enterprise – Live
(Hardware refresh in live environment)
Project expectations include:
- Work will be done outside normal business hours
- Your company will tag assets to be decommissioned
- Agreement on disposition of rail kits, rack PDUs, cords
- Is installation of blanking plates required?
Colocation
(Cage cleanout)
Completed project includes:
- Coordination with building management if needed
- Vacate space
- Remove cabling
- Broom swept clean space
Let’s Collaborate
We handle full data center decommissions. From racks to secure data destruction to asset resale and recycling.